THE SENATE |
S.B. NO. |
2474 |
THIRTY-FIRST LEGISLATURE, 2022 |
S.D. 2 |
|
STATE OF HAWAII |
H.D. 1 |
|
|
|
|
|
||
|
A BILL FOR AN ACT
RELATING TO RENEWABLE ENERGY.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The legislature finds that accelerating the development of renewable energy to reduce greenhouse gases is a high priority. The legislature has enacted numerous Acts to achieve this objective, including:
(1) Act 97, Session Laws of Hawaii 2015, which established a renewable energy portfolio standards target of one hundred per cent renewable electric energy by 2045;
(2) Act 15, Session Laws of Hawaii 2018, which established a statewide zero emissions clean economy target to sequester throughout the State more atmospheric carbon and greenhouse gases than emitted, as quickly as practicable but no later than 2045; and
(3) Act 23, Session Laws of Hawaii 2020, which prohibits the further use of coal in Hawaii for electricity production.
The legislature believes that the timely completion of renewable energy projects is also a high priority.
The legislature recognizes that in November 2020, the public utilities commission issued a letter to the parties in docket numbers 2015-0389, 2017-0352, and 2018-0165, stating that it "is markedly concerned that Hawaiian Electric [Company]'s interconnection processes and policies are increasing development costs and extending renewable project timelines".
In addition, in docket number 2018-0088 (Performance Based Regulation), the public utilities commission issued order number 37507 on December 23, 2020, indicating that the commission was concerned about interconnection delays and will implement a performance incentive mechanism to encourage Hawaiian Electric Company to accelerate the interconnection process. Order number 37507 also stated that "the scheduled retirement of the AES Power Plant in 2022, as well as [Hawaiian Electric Company, Inc.; Hawaii Electric Light Company, Inc.; and Maui Electric Company, Limited's] proposal to delay interconnecting several renewable energy and storage projects recently approved by the commission, underscores the need for expeditiously securing alternative sources of grid services to ensure that system needs are met".
The legislature notes that during procurement phase 1, all eight projects had delayed commercial operations dates relative to the commercial operations dates provided in each project's power purchase agreement. During procurement phase 2, eight of the eleven projects had delayed commercial operations dates relative to the commercial operations dates provided in each project's power purchase agreement. The public utilities commission has opened a docket, docket number 2021-0024, to review Hawaiian Electric Company's interconnection process and transition plans for retirement of fossil fuel plants.
The legislature further notes that Hawaiian Electric Company's significant delays in completing its interconnection process makes it difficult to plan for the design and construction of utility-scale renewable energy projects that require interconnection with Hawaiian Electric Company's electric grid.
The legislature further finds that facilitating the timely interconnection of utility-scale renewable energy projects will:
(1) Help to bring utility-scale renewable energy projects online sooner;
(2) Decrease electricity rates for consumers by providing project developers with added certainty regarding project timelines to lower bid pricing;
(3) Help to achieve the State's renewable portfolio standard goals in a timely manner; and
(4) Help to reduce greenhouse gas emissions and mitigate the effects of climate change sooner.
Accordingly, the purpose of this Act is to facilitate the timely interconnection of utility-scale renewable energy projects.
SECTION 2. Section 269-142, Hawaii Revised Statutes, is amended by amending subsections (a) and (b) to read as follows:
"(a) The commission [may] shall adopt, by
rule or order, reliability standards and interconnection requirements. Reliability standards and interconnection
requirements adopted by the commission shall apply to any electric utility and
any user, owner, or operator of the Hawaii electric system. The commission shall not contract for the
performance of the functions under this subsection to any other entity as
provided under section 269-147.
(b)
The commission [may] shall develop reliability standards and
interconnection requirements as it determines necessary or upon recommendation
from any entity, including an entity contracted by the commission to serve as
the Hawaii electricity reliability administrator provided for under this part,
for the continuing reliable design and operation of the Hawaii electric system.
Any reliability standard or
interconnection requirement developed by the commission shall be adopted by the
commission in accordance with subsection (a) in order to be effective. The commission shall not contract for the
performance of the functions under this subsection to any other entity as
provided under section 269-147."
SECTION 3. Section 269-145, Hawaii Revised Statutes, is amended to read as follows:
"[[]§269-145[]] Grid access; procedures for interconnection;
dispute resolution. (a) Each user, owner, or operator of the Hawaii
electric system, or any other person, business, or entity seeking to make an interconnection
on the Hawaii electric system shall do so in accordance with procedures to be established
by the commission by rule or order.
(b)
The commission shall establish interconnection procedures as follows:
(1) The commission
shall include in any interconnection procedures established pursuant to this
section requirements that the electric public utilities:
(A) Complete
the interconnection design;
(B) Reach
agreement with the renewable energy project developer;
(C) File
a request with the commission for interconnection or line extension approval,
if required;
(D) Meet
the requirements under subparagraphs (A) through (C) as soon as practicable;
(E) Meet
timelines and deadlines as determined by the commission; and
(F) Submit
interim reports to the commission on the status of the electric public
utility's efforts to comply with the requirements of this subsection ninety
days and one hundred eighty days after the renewable energy project power
purchase agreement is filed with the commission for review and approval;
(2) If the electric
public utility is unable to comply with the requirements of this subsection, the
electric public utility shall report, in writing, the reasons for noncompliance
to the commission within ten calendar days after the failure to meet timelines and
deadlines established by the commission;
(3) If the electric
public utility fails to meet the requirements established by the commission
pursuant to this subsection, the electric public utility shall forfeit and
return all moneys or other financial incentives that the electric public
utility has received as part of any performance incentive mechanism program or
similar incentive-based award recognized by the commission in connection with the
renewable energy project; and
(4) The commission
shall submit a report to the governor and legislature regarding any failure to
meet the timing under this subsection by any electric public utility within thirty
days of the commission receiving notice of this failure;
provided
that this subsection shall only apply to utility-scale renewable energy
projects that are five megawatts in total output capacity or larger, and
to any community-based renewable energy project.
[(b)] (c) The commission shall have the authority to
make final determinations regarding any dispute between any user, owner, or
operator of the Hawaii electric system, or any other person, business, or
entity connecting to the Hawaii electric system, concerning either an existing
interconnection on the Hawaii electric system or an interconnection to the
Hawaii electric system created under the processes established by the commission
under this section."
SECTION 4. Section 269-146, Hawaii Revised Statutes, is amended by amending subsection (a) to read as follows:
"(a) The commission may require, by rule or order,
that [all] any utilities, persons, businesses, or entities
connecting to the Hawaii electric system, or any other user, owner, or operator
of any electric element that is a part of an interconnection on the Hawaii
electric system [shall] pay a surcharge that shall be collected by
Hawaii's electric
utilities. The commission shall not
contract or otherwise delegate the ability to create the Hawaii electricity
reliability surcharge under this section to any other entity. This surcharge amount shall be known as the
Hawaii electricity reliability surcharge."
SECTION 5. Statutory material to be repealed is bracketed and stricken. New statutory material is underscored.
SECTION 6. This Act shall take effect on July 1, 2100.
Report Title:
Renewable Energy; Reliability Standards; Interconnection Requirements; PUC
Description:
Requires the Public Utilities Commission to establish reliability standards and interconnection requirements for renewable energy projects and community-based renewable energy projects. Effective 7/1/2100. (HD1)
The summary description
of legislation appearing on this page is for informational purposes only and is
not legislation or evidence of legislative intent.