| Measure Title: | RELATING TO UTILITY LINES. |
| Report Title: | Utility Lines; Construction Moratorium; Advisory Committee ($) |
| Description: | Establishes a three-year moratorium on the construction and installation of forty-six kilovolt or greater high-voltage electric transmission lines. Establishes an advisory committee to develop a statewide utility undergrounding plan and submit reports (interim: 2004, final: 2005). |
| Package: | None |
| Companion: | |
| Introducer(s): | TANIGUCHI |
| Current Referral: | CPH/ENE, WAM |
| Date | Status Text | |
|---|---|---|
| 1/17/2003 | S | Introduced and passed First Reading. |
| 1/22/2003 | S | Referred to CPH/ENE, WAM. |
| 8/21/2003 | D | Carried over to 2004 Regular Session. |
$ = Appropriation measure