| Measure Title: | RELATING TO CONSTRUCTION CLAIMS. |
| Report Title: | Contractors Opportunity to Repair |
| Description: | Allows contractors the opportunity to repair construction defects prior to litigation; outlines process to be followed before litigation is filed. |
| Package: | None |
| Companion: | |
| Introducer(s): | SAY (BR) |
| Current Referral: | CPC/JUD |
| Date | Status Text | |
|---|---|---|
| 1/28/2004 | H | Introduced and Pass First Reading |
| 2/2/2004 | H | Referred to CPC/JUD, referral sheet 6 |
| 2/3/2004 | H | Bill scheduled to be heard by CPC/JUD on Thursday, 02-05-04 at 3:30 pm in House conference room 325. |
| 2/6/2004 | H | The committee(s) recommends that the measure be deferred. |
$ = Appropriation measure
ConAm = Constitutional Amendment