Measure Title: | RELATING TO UTILITY LINES. |
Report Title: | Utility Lines; Construction and Installation Moratorium |
Description: | Establishes a 3-year moratorium on the construction and installation of 138 kilovolt or greater high-voltage electric transmission lines or systems. |
Package: | None |
Companion: | |
Introducer(s): | TANIGUCHI |
Current Referral: | WLE, CPH |
Date | Status Text | |
---|---|---|
1/18/2002 | S | Introduced and passed First Reading. |
1/25/2002 | S | Referred to WLE, CPH. |
2/1/2002 | S | Bill scheduled to be heard by WLE on 02-06-02 at 1:30 pm in conference room 224. |
2/6/2002 | S | The committee(s) on WLE recommend(s) that the measure be PASSED, UNAMENDED. |
2/6/2002 | S | The votes in WLE were as follows: 7 Aye(s): Senator(s) Inouye, Chun Oakland, English, Ihara, Kokubun, Nakata, Hemmings; Aye(s) with reservations: none ; 0 No(es): none; and 2 Excused: Senator(s) Chun, Matsunaga. |
2/12/2002 | S | Reported from WLE (Stand. Com. Rep. No. 2120) with recommendation of passage on Second Reading and referral to CPH. Report adopted, Passed Second Reading and referred to CPH. |
$ = Appropriation measure
ConAm = Constitutional Amendment