Report Title:
CIP; 41ST Representative District
Description:
Appropriates funds for capital improvement projects for the benefit of the 41st representative district.
HOUSE OF REPRESENTATIVES |
H.B. NO. |
2712 |
TWENTY-FIRST LEGISLATURE, 2002 |
||
STATE OF HAWAII |
||
|
A BILL FOR AN ACT
RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE FORTY-FIRST REPRESENTATIVE DISTRICT.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2002-2003:
1. To be expended by the department of accounting and general services:
A. Campbell high school, Oahu
Design, construction,, and equipment to install air-conditioning for entire school.
Design $ 600,000
Construction 10,000,000
Equipment 543,000
Total funding $ 11,143,000
B. Campbell high school, Oahu
Design and construction for parking lighting improvement.
Design $ 5,000
Construction 100,000
Total funding $ 105,000
C. Campbell high school, Oahu
Design, construction, and equipment for a woman's locker room.
Design $ 200,000
Construction 3,400,000
Equipment 20,000
Total funding $ 3,620,000
D. Campbell high school, Oahu
Design and construction of permanent bleachers for football field.
Design $ 200,000
Construction 3,780,000
Total funding $ 3,980,000
E. Campbell high school, Oahu
Design and construction for four tennis courts.
Design $ 30,000
Construction 180,000
Total funding $ 210,000
F. Campbell high school, Oahu
Design and construction for scoreboard at softball field.
Design $ 20,000
Construction 123,000
Total funding $ 143,000
G. Campbell high school, Oahu
Design and construction for scorer's booth for softball field.
Design $ 5,000
Construction 40,000
Total funding $ 45,000
H. Campbell high school, Oahu
Design and construction for announcer's booth with elevator for football program.
Design $ 40,000
Construction 360,000
Total funding $ 400,000
I. Ewa Beach elementary school, Oahu
Design, construction, and equipment for six-classroom building to replace portables.
Design $ 300,000
Construction 2,500,000
Equipment 100,000
Total funding $ 2,900,000
J. Ewa Beach elementary school, Oahu
Design and construction to install air-conditioning for entire school.
Design $ 170,000
Construction 2,652,000
Total funding $ 2,822,000
K. Ewa Beach elementary school, Oahu
Design and construction to renovate and upgrade electrical system.
Design $ 40,000
Construction 380,000
Total funding 420,000
L. Ewa Beach elementary school, Oahu
Design and construction to convert kitchen and dining hall into classroom.
Design $ 80,000
Construction 915,000
Total funding $ 995,000
M. Ewa elementary school, Oahu
Design and construction to install air-conditioning for entire school.
Design $ 170,000
Construction 2,652,000
Total funding $ 2,822,000
N. Ewa elementary school, Oahu
Construction to replace glass windows in bldg. L.
Construction $ 20,000
Total funding $ 20,000
O. Ewa elementary school, Oahu
Construction to install air-conditioning for bldg. L.
Construction $ 350,000
Total funding $ 350,000
P. Ewa elementary school, Oahu
Construction to install air-conditioning for bldg. I.
Construction $ 750,000
Total funding $ 750,000
Q. Holomua elementary school, Oahu
Design and construction to install concrete slab
between building E and K-2 playground equipment.
Design $ 2,000
Construction 18,000
Total funding $ 20,000
R. Ilima intermediate school, Oahu
Design, construction, and equipment to install air-conditioning for entire school.
Design $ 300,000
Construction 4,800,000
Equipment 52,000
Total funding $ 5,152,000
S. Ilima intermediate school, Oahu
Design and construction for landscaping and installation of water system throughout the campus.
Design $ 10,000
Construction 190,000
Total funding $ 200,000
T. Ilima intermediate school, Oahu
Design and construction to install traffic signals on Ft. Weaver Rd. in front of Ilima intermediate school.
Design $ 15,000
Construction 290,000
Total funding $ 305,000
U. Ilima intermediate school, Oahu
Design and construction for repair of parking lot.
Design $ 11,000
Construction 200,000
Total funding $ 211,000
V. Iroquois Point elementary school, Oahu
Design and construction for a physical education center to benefit grades K-6.
Design $ 3,000
Construction 22,000
Total funding $ 25,000
W. Iroquois Point elementary school, Oahu
Design and construction for a driveway and fifteen cars capacity parking lot with a turn around for special education buses.
Design $14,000
Construction 86,000
Total funding $100,000
X. Kaimiloa elementary school, Oahu
Design, construction, and equipment for an eight-classroom building to replace classes in portables.
Design $ 200,000
Construction 2,750,000
Equipment 60,000
Total funding $ 3,010,000
Y. Kaimiloa elementary school, Oahu
Design and construction to install air-conditioning for entire school.
Design $ 220,000
Construction 4,230,000
Total funding $ 4,450,000
Z. Ocean Pointe elementary school, Oahu
Design and construction for school.
Design $ 100,000
Construction 1,100,000
Total funding $ 1,200,000
AA. Pohakea elementary school, Oahu
Design and construction to install air-conditioning for entire school.
Design $ 450,000
Construction 3,813,000
Total funding $ 4,263,000
BB. Pohakea elementary school, Oahu
Design and construction for renovations to administration building.
Design $ 3,000
Construction 11,000
Total funding $ 14,000
CC. Waipahu intermediate school, Oahu
Design, construction, and equipment for a cafetorium.
Design $ 270,000
Construction 2,600,000
Equipment 125,000
Total funding $ 2,995,000
DD. Waipahu intermediate school, Oahu
Design, construction, and equipment for an eight- classroom building.
Design $ 200,000
Construction 2,750,000
Equipment 60,000
Total funding $ 3,010,000
2. To be expended by the department of transportation:
A. Sidewalk for Ft. Weaver Road, Oahu
Design and construction to install sidewalk from Geiger Road to Ewa Family Center, which includes Pedestrian Footbridge/Ewa side of Ft. Weaver Road.
Design $ 150,000
Construction 1,000,000
Total funding $ 1,150,000
B. Traffic light cameras on Fort Weaver road, Oahu
Design, construction, and equipment for installation of traffic light cameras between Laulaunui Street and Old Fort Weaver road to check traffic flow.
Design $ 1,000
Construction 658,000
Equipment 1,000
Total funding $ 660
C. Intra-island commuter ferry project, Oahu
Plans, design, and construction for commuter ferry improvements at Barbers Point, Middle Loch, and Iroquois Point.
Plans $1,000
Design 1,000
Construction 998,000
Total funding $1,000,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agencies for the purposes of this Act.