SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2002-2003:
1. To be expended by the department of accounting and general services:
A. McKinley high school, Oahu
Design and construction to conform W building with the Americans with Disabilities Act.
Design $400,000
Construction $4,600,000
Total funding $5,000,000
B. McKinley high school, Oahu
Design and construction to modernize the electrical system.
Design $300,000
Construction $1,100,000
Total funding $1,400,000
C. McKinley high school, Oahu
Construction and equipment for a double-sink in the gym concession area.
Construction $22,000
Equipment $3,000
Total funding $25,000
D. McKinley high school, Oahu
Design and construction of cooling and ventilation fans in gym.
Design $10,000
Construction $290,000
Total funding $300,000
E. McKinley high school, Oahu
Design and construction to upgrade the physical education sports facility to provide gender equity.
Design $200,000
Construction $2,200,000
Total funding $2,400,000
F. McKinley high school, Oahu
Design and construction to modernize and replace the antiquated plumbing system.
Design $90,000
Construction $730,000
Total funding $820,000
G. Central middle school, Oahu
Design and construction to implement the facilities building program, building A.
Design $250,000
Construction $5,300,000
Total funding $5,550,000
H. Central middle school, Oahu
Design, construction, and equipment to replace and equip the cafeteria, auditorium, library, and classrooms.
Design $1,000,000
Construction $9,000,000
Equipment $1,500,000
Total funding $11,500,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.