REPORT TITLE:
CIP; 16th Senatorial District


DESCRIPTION:
Appropriates funds for various capital improvement projects in
the 16th senatorial district.

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
                                                        3149
THE SENATE                              S.B. NO.           
TWENTIETH LEGISLATURE, 2000                                
STATE OF HAWAII                                            
                                                             
________________________________________________________________
________________________________________________________________


                   A  BILL  FOR  AN  ACT

AUTHORIZING THE ISSUANCE OF GENERAL OBLIGATION BONDS AND MAKING
   AN APPROPRIATION FOR CAPITAL IMPROVEMENT PROJECTS IN THE
   16TH SENATORIAL DISTRICT.



BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 1      SECTION 1.  The director of finance is authorized to issue
 
 2 general obligation bonds in the sum of $26,748,500, or so much
 
 3 thereof as may be necessary, and the same sum, or so much thereof
 
 4 as may be necessary, is appropriated for fiscal year 2000-2001,
 
 5 for the following projects:
 
 6  1.  Aliamanu elementary school, Oahu
 
 7           Design, construction, and equipment for
 
 8           a handicapped-accessible restroom in
 
 9           the health room.                            $    50,000
 
10  2.  Aliamanu intermediate school, Oahu
 
11           Upgrade electrical system to provide
 
12           more power for technology and related
 
13           activities.                                 $   250,000
 
14  3.  Hickam elementary school, Oahu
 
15           Expansion of library facility to
 
16           accommodate increased school population
 
17           and facilitate effectiveness.               $ 1,000,000
 
18  4.  Hickam elementary school, Oahu
 

 
Page 2                                                     3149
                                     S.B. NO.           
                                                        
                                                        

 
 1           Renovate cafeteria to facilitate timely
 
 2           and efficient lunch time operations.        $   830,000
 
 3  5.  Hickam elementary school, Oahu
 
 4           Upgrade electrical system to provide
 
 5           more power for technology-related
 
 6           activities.                                 $   500,000
 
 7  6.  Makalapa elementary school, Oahu
 
 8           Renovate and expand cafeteria to
 
 9           minimize staggered lunch hour and to
 
10           accommodate student population.             $   915,000
 
11  7.  Makalapa elementary school, Oahu
 
12           Replace deteriorated and hazardous
 
13           exterior concrete overhangs in
 
14           buildings D, F, & I for safety reasons.     $   300,000
 
15  8.  Moanalua intermediate school, Oahu
 
16           Planning, design, construction, and
 
17           equipment to provide and upgrade
 
18           electrical system for technology and
 
19           related activities in five multipurpose
 
20           rooms and for air conditioning to
 
21           reclaim usable teaching spaces.             $   885,000
 
22  9.  Moanalua high school, Oahu
 
23           Purchase equipment to complete full use
 

 
Page 3                                                     3149
                                     S.B. NO.           
                                                        
                                                        

 
 1           of the multimedia & computer center.        $   375,000
 
 2 10.  Moanalua high school, Oahu
 
 3           Planning, design, and construction for
 
 4           a performing arts center.                   $10,000,000
 
 5 11.  Moanalua high school, Oahu
 
 6           Planning, design, and construction for
 
 7           an alternative education facility,
 
 8           including the replacement of two
 
 9           existing portables.                         $ 5,000,000
 
10 12.  Moanalua elementary school, Oahu
 
11           Construction of concrete walkways to
 
12           prevent children from walking in dirt
 
13           and mud to and from portable
 
14           classrooms, and buildings F, P1, P4,
 
15           P5, A10, and P7.                            $    13,000
 
16 13.  Moanalua elementary school, Oahu
 
17           Provide roofing over existing walkways
 
18           for health and well-being of the
 
19           children.                                   $    28,500
 
20 14.  Moanalua elementary school, Oahu
 
21           Planning, design, and construction to
 
22           expand the main parking lot to
 
23           alleviate inadequate parking.               $    25,000
 

 
Page 4                                                     3149
                                     S.B. NO.           
                                                        
                                                        

 
 1 15.  Moanalua elementary school, Oahu
 
 2           Renovate and expand library to provide
 
 3           a technology center, and student and
 
 4           teacher work areas.                         $   100,000
 
 5 16.  Moanalua elementary school, Oahu
 
 6           Planning, design, and construction for
 
 7           eight classrooms on top of building F
 
 8           to replace eight existing portable
 
 9           classrooms.                                 $   800,000
 
10 17.  Admiral Chester W. Nimitz elementary school,
 
11        Oahu
 
12           Design, construction, and equipment for
 
13           an air conditioning system in building
 
14           C (twenty classrooms).                      $   100,000
 
15 18.  Pearl Harbor elementary school, Oahu
 
16           Design and construction to expand an
 
17           undersized library.                         $   700,000
 
18 19.  Pearl Harbor Kai elementary school, Oahu
 
19           Renovate library, upgrade electrical
 
20           system, and provide air conditioning to
 
21           mitigate anticipated noise and dust
 
22           problems emanating from a major Navy
 
23           housing project located adjacent to
 

 
Page 5                                                     3149
                                     S.B. NO.           
                                                        
                                                        

 
 1           school.                                     $   450,000
 
 2 20.  Pu'uhale elementary school, Oahu
 
 3           Resurface Kanakanui street.                 $   330,000
 
 4 21.  Pu'uhale elementary school, Oahu
 
 5           Design and construction for a covered
 
 6           walkway to buildings A and B.               $   330,000
 
 7 22.  Pu'uhale elementary school, Oahu
 
 8           Design and installation of security
 
 9           screens for cafeteria.                      $   165,000
 
10 23.  Salt Lake elementary school, Oahu
 
11           Design and construction to renovate
 
12           interior classrooms on top floor of
 
13           building E and F and to provide air
 
14           conditioning.                               $   964,000
 
15 24.  Salt Lake elementary school, Oahu
 
16           Construction of a covered walkway from
 
17           building C to cafeteria.                    $    50,000
 
18 25.  Admiral Arthur W. Radford high school, Oahu
 
19           Design, construction, and equipment for
 
20           a training/rehabilitation classroom to
 
21           expand health care services curriculum.     $   526,000
 
22 26.  Admiral Arthur W. Radford high school, Oahu
 
23           Design, construction, and equipment to
 

 
Page 6                                                     3149
                                     S.B. NO.           
                                                        
                                                        

 
 1           expand the weight-training room.            $   593,000
 
 2 27.  Admiral Arthur W. Radford high school, Oahu
 
 3           Planning, design, and renovation of
 
 4           restrooms.                                  $   850,000
 
 5 28.  Admiral Arthur W Radford high school, Oahu
 
 6           Plan, design, and renovate science
 
 7           classrooms.                                 $   300,000
 
 8 29.  Red Hill elementary school, Oahu
 
 9           Construction of covered walkways to
 
10           cafeteria, library, computer lab, and
 
11           office.                                     $   131,000
 
12 30.  Red Hill elementary school, Oahu
 
13           Completion of local area network
 
14           electrical system for ten classrooms.       $    15,000
 
15 31.  Red Hill elementary school, Oahu
 
16           Design and installation of a new
 
17           sprinkler system to mitigate the
 
18           erosion of hilly areas of the school.       $    23,000
 
19 32.  Aloha stadium, Oahu
 
20           Design, landscape, and install
 
21           irrigative systems along perimeter
 
22           fencing at stadium, Kamehameha highway
 
23           parking lot, and Hawaii housing
 

 
Page 7                                                     3149
                                     S.B. NO.           
                                                        
                                                        

 
 1           authority.                                  $   150,000
 
 2      SECTION 2.  The sum appropriated shall be expended by the
 
 3 department of accounting and general services for the purposes of
 
 4 the capital improvement projects described in section 1 of this
 
 5 Act.
 
 6      SECTION 3.  This Act shall take effect on July 1, 2000.
 
 7 
 
 8                           INTRODUCED BY:  _______________________