REPORT TITLE:
CIP for the 26th Rep. District


DESCRIPTION:
Appropriates funds relating to capital improvement projects for
the benefit of the 26th representative district.

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
                                                        2954
HOUSE OF REPRESENTATIVES                H.B. NO.           
TWENTIETH LEGISLATURE, 2000                                
STATE OF HAWAII                                            
                                                             
________________________________________________________________
________________________________________________________________


                   A  BILL  FOR  AN  ACT

RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE
   TWENTY-SIXTH REPRESENTATIVE DISTRICT.



BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 1      SECTION 1.  The following sums, or so much thereof as shall
 
 2 be sufficient to finance the projects listed in this Act, are
 
 3 hereby appropriated out of the general revenues of the State of
 
 4 Hawaii for fiscal year 2000-2001.
 
 5      A.   Kawananakoa intermediate school, Oahu
 
 6           Design and construction of a covered student lanai with
 
 7           tables, chairs, and a security fence to enclose the
 
 8           entire lanai.
 
 9           Design                                 $         50,000
 
10           Construction                                    250,000
 
11           Total funding                                   300,000
 
12      B.   Kawananakoa intermediate school, Oahu
 
13           Design and construction for the resurfacing of the
 
14           parking lot to include speed bumps and painting lines
 
15           on the lower half.
 
16           Design                                           19,000
 
17           Construction                                     92,000
 
18           Total funding                                   111,000
 

 
Page 2                                                     2954
                                     H.B. NO.           
                                                        
                                                        

 
 1      C.   Kawananakoa intermediate school, Oahu
 
 2           Develop a landscape master plan.
 
 3           Plans                                            50,000
 
 4           Total funding                                    50,000
 
 5      D.   Lincoln elementary school, Oahu
 
 6           Design and construction for safe playground surfacing
 
 7           materials and frames for existing play apparatus as
 
 8           well as wheelchair accessibility.
 
 9           Design                                           15,000
 
10           Construction                                     60,000
 
11           Total funding                                    75,000
 
12      E.   Lincoln elementary school, Oahu
 
13           Design and construction of a parking lot.
 
14           Design                                           25,000
 
15           Construction                                    100,000
 
16           Total funding                                   125,000
 
17      F.   Lincoln elementary school, Oahu
 
18           Design and construction for the reroofing of Building
 
19           E.
 
20           Design                                           14,000
 
21           Construction                                     56,000
 
22           Total funding                                    70,000
 

 
 
 
Page 3                                                     2954
                                     H.B. NO.           
                                                        
                                                        

 
 1      G.   Lincoln Elementary School, Oahu
 
 2           Design and construction for new drain lines in the
 
 3           kitchen.
 
 4           Design                                           20,000
 
 5           Construction                                     80,000
 
 6           Total funding                                   100,000
 
 7      H.   Maemae elementary school, Oahu
 
 8           Design and construction for drainage around walkways
 
 9           and playground.
 
10           Design                                            1,000
 
11           Construction                                    599,000
 
12           Total funding                                   600,000
 
13      I.   Maemae elementary school, Oahu
 
14           Plans, design, and construction of a library.
 
15           Plans                                             1,000
 
16           Design                                            1,000
 
17           Construction                                  1,798,000
 
18           Total funding                                 1,800,000
 
19      J.   Maemae elementary school, Oahu
 
20           Plans, design, and construction of a rock wall.
 
21           Plans                                             1,000
 
22           Design                                            1,000
 
23           Construction                                      8,000
 
24           Total funding                                    10,000
 

 
Page 4                                                     2954
                                     H.B. NO.           
                                                        
                                                        

 
 1      K.   McKinley high school, Oahu
 
 2           Construction of new building for physical education
 
 3           classrooms and girl's athletic lockers to meet title
 
 4           VIII needs.
 
 5           Construction                                  3,500,000
 
 6           Total funding                                 3,500,000
 
 7      L.   McKinley high school, Oahu
 
 8           Construction to expand existing facilities in the auto
 
 9           and electronics shops.
 
10           Construction                                  4,000,000
 
11           Total funding                                 4,000,000
 
12      M.   Nuuanu elementary school, Oahu
 
13           Design and construction to landscape the hilly area
 
14           surrounding the blacktop and to install a turn-around
 
15           adjacent to the gym.
 
16           Design                                           26,000
 
17           Construction                                    217,000
 
18           Total funding                                   243,000
 
19      N.   Pauoa elementary school, Oahu
 
20           Plan, design, and construction to add a drop-off and
 
21           turn-around area for the parking lot.
 

 
 
 
 
 
Page 5                                                     2954
                                     H.B. NO.           
                                                        
                                                        

 
 1           Plans                                             1,000
 
 2           Design                                            1,000
 
 3           Construction                                     98,000
 
 4           Total funding                                   100,000
 
 5      O.   Royal elementary school, Oahu
 
 6           Construction of an electrical system.
 
 7           Construction                                      4,000
 
 8           Total funding                                     4,000
 
 9      P.   Stevenson intermediate school, Oahu
 
10           Plan, design, construction, and equipment for the
 
11           installation of metal gates, screen tiles, and railings
 
12           for Building A to prevent trespassers from entering.
 
13           Plans                                            40,000
 
14           Design                                           40,000
 
15           Construction                                    180,000
 
16           Equipment                                        35,000
 
17           Total funding                                   295,000
 
18      SECTION 2.  The sums appropriated for the respective capital
 
19 projects set forth in section 1 shall expended by the department
 
20 of accounting and general services for the purposes of this Act.
 

 
 
 
 
 
 
 
Page 6                                                     2954
                                     H.B. NO.           
                                                        
                                                        

 
 1      SECTION 3.  This Act shall take effect on July 1, 2000.
 
 2 
 
 3                       INTRODUCED BY:  ___________________________