REPORT TITLE:
CIP for the 28th District


DESCRIPTION:
CIP for the 28th Representative District.

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
                                                        
HOUSE OF REPRESENTATIVES                H.B. NO.1694       
TWENTIETH LEGISLATURE, 1999                                
STATE OF HAWAII                                            
                                                             
________________________________________________________________
________________________________________________________________


                   A  BILL  FOR  AN  ACT

RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE
   TWENTY-EIGHTH REPRESENTATIVE DISTRICT.


BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 1      SECTION 1.  The following sums, or so much thereof as shall
 
 2 be sufficient to finance the projects listed in this Act, are
 
 3 hereby appropriated out of the general revenues of the State of
 
 4 Hawaii for fiscal year 1999-2000.
 
 5 1.  To be expended by the department of accounting and general
 
 6 services:
 
 7      A.   Dole intermediate school, Oahu
 
 8           Plans, design, and construction of a 90' X 100' lighted
 
 9           overflow parking and play area at the rear of the
 
10           campus between the shop and music buildings.
 
11           Plans                                          $  1,000
 
12           Design                                            3,000
 
13           Construction                                     45,000
 
14           Total funding                                    49,000
 
15      B.   Dole intermediate school, Oahu
 
16           Plans, design, and construction to install student
 
17           physical education lockers.
 

 
 
Page 2                                                     
                                     H.B. NO.1692       
                                                        
                                                        

 
 1           Plans                                          $  1,000
 
 2           Design                                            4,000
 
 3           Construction                                     50,000
 
 4           Total funding                                    55,000
 
 5      C.   Dole intermediate school, Oahu
 
 6           Plans, design, and construction to renovate building
 
 7           walls and sidewalks.
 
 8           Plans                                          $ 20,000
 
 9           Design                                           30,000
 
10           Construction                                    500,000
 
11           Total funding                                   550,000
 
12      D.   Farrington high school, Oahu
 
13           Plans, design, and construction to renovate and upgrade
 
14           the auditorium.
 
15           Plans                                          $ 20,000
 
16           Design                                           20,000
 
17           Construction                                  1,900,000
 
18           Total funding                                 1,940,000
 
19      E.   Farrington high school, Oahu
 
20           Plans, design, and construction to install a tartan
 
21           surface track at Kusunoki field.
 

 
 
 
 
 
Page 3                                                     
                                     H.B. NO.1692       
                                                        
                                                        

 
 1           Plans                                          $  5,000
 
 2           Design                                           25,000
 
 3           Construction                                    500,000
 
 4           Total funding                                   530,000
 
 5      F.   Farrington high school, Oahu
 
 6           Plans, design, and construction to replace the chain
 
 7           link fence along King street with hedges.
 
 8           Plans                                          $  1,000
 
 9           Design                                            1,000
 
10           Construction                                     20,000
 
11           Total funding                                    22,000
 
12      G.   Farrington high school, Oahu
 
13           Plans, design, and construction to widen the Kalihi
 
14           street gate, improve roadway entrance, and install
 
15           sidewalks.
 
16           Plans                                          $  2,000
 
17           Design                                            6,000
 
18           Construction                                     88,000
 
19           Total funding                                    96,000
 
20      H.   Kalihi elementary school, Oahu
 
21           Plans, design, and construction to replace the
 
22           playground equipment, repave the area, and install
 
23           padded groundcover under the equipment.
 

 
Page 4                                                     
                                     H.B. NO.1692       
                                                        
                                                        

 
 1           Plans                                          $  1,000
 
 2           Design                                            4,000
 
 3           Construction                                     95,000
 
 4           Total funding                                   100,000
 
 5      I.   Kalihi elementary school, Oahu
 
 6           Plans, design, and construction to replace the upper
 
 7           playground equipment, repave the area, and install
 
 8           padded groundcover under the equipment.
 
 9           Plans                                          $  1,000
 
10           Design                                            4,000
 
11           Construction                                     40,000
 
12           Total funding                                    45,000
 
13      J.   Kalihi elementary school, Oahu
 
14           Plans, design, and construction to install loading
 
15           ramps at the cafeteria and administration building.
 
16           Plans                                          $  1,000
 
17           Design                                            4,000
 
18           Construction                                     70,000
 
19           Total funding                                    75,000
 

 
 
 
 
 
 
 
 
 
Page 5                                                     
                                     H.B. NO.1692       
                                                        
                                                        

 
 1      K.   Kapalama elementary school, Oahu
 
 2           Design and construction to install padded groundcover
 
 3           under playground equipment.
 
 4           Design                                         $  2,000
 
 5           Construction                                     33,000
 
 6           Total funding                                    35,000
 
 7      L.   Fern elementary school, Oahu
 
 8           Plans, design, and construction to upgrade the
 
 9           electrical power and telephone source for new education
 
10           technology.
 
11           Plans                                          $  1,000
 
12           Design                                            1,000
 
13           Construction                                      8,000
 
14           Total funding                                    10,000
 
15      M.   Kalihi uka elementary school, Oahu
 
16           Plans, design, and construction of a drop-off and
 
17           drive-through area at the Lehua street entrance,
 
18           expansion of the parking lot on to the grassy area, and
 
19           reconfiguration for auto and pedestrian traffic safety.
 
20           Plans                                          $ 10,000
 
21           Design                                           34,000
 
22           Construction                                    443,000
 
23           Total funding                                   487,000
 

 
Page 6                                                     
                                     H.B. NO.1692       
                                                        
                                                        

 
 1 2.  To be expended by the department of land and natural
 
 2 resources:
 
 3      A.   Kalihi valley natural history park, Oahu
 
 4           Plans, design, and construction for the development of
 
 5           Kalihi valley natural history park.
 
 6           Plans                                          $ 10,000
 
 7           Design                                           90,000
 
 8           Construction                                  1,900,000
 
 9           Total funding                                 2,000,000
 
10 3.  To be expended by the city and county of Honolulu:
 
11      A.   Kalihi street between Monte street and Numana road,
 
12           Oahu
 
13           Plans, design, and construction for asphalt sidewalk
 
14           improvements on Kalihi street between Monte street and
 
15           Numana road, and on Nihi street.
 
16           Plans                                          $  5,000
 
17           Design                                           20,000
 
18           Construction                                    250,000
 
19           Total funding                                   275,000
 
20      B.   Nihi street, Oahu
 
21           Plans, design, and construction for general
 
22           improvements and a drainage system for the unimproved
 
23           portions of Nihi street.
 

 
Page 7                                                     
                                     H.B. NO.1692       
                                                        
                                                        

 
 1           Plans                                          $  1,000
 
 2           Design                                            1,000
 
 3           Construction                                    998,000
 
 4           Total funding                                 1,000,000
 
 5      SECTION 2.  The sums appropriated for the respective capital
 
 6 improvement projects set forth in section 1 shall be expended by
 
 7 the designated expending agency for the purposes of this Act;
 
 8 provided that funds from item (3)(A) shall be matched by the city
 
 9 and county of Honolulu.
 
10      SECTION 3.  This Act shall take effect on July 1, 1999.
 
11 
 
12                           INTRODUCED BY:  _______________________