     SECTION 1.  The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2024-2025:

      1.  Kaiser high school, Oahu

      A.  Modernize network infrastructure and unified communications to provide for outdoor speakers, indoor paging, and an audio bell system.

          Design:                                $175,000

          Construction:                          $1,000,000

          Equipment:                             $325,000

          Total funding:                         $1,500,000

      B.  Design and construct performing and visual arts complex.

          Design:                                $7,750,000

          Construction:                          $44,250,000

          Total funding:                         $52,000,000

   C.  Modernize swimming pool system and facility to install chemical and filtration equipment, convert lighting to LED, install hand railing to bleachers, and renovate locker rooms and pool offices.

          Design:                                $345,000

          Construction:                          $2,300,000

          Total funding:                         $2,645,000

      D.  Replacement of schoolwide public address system.

          Plans and Design:                      $250,000

          Equipment:                             $1,750,000

          Total funding:                         $2,000,000

  E.  Erosion control efforts at Kaiser Stadium West, softball venues, and baseball venues.

          Design:                                $120,000

          Construction:                          $800,000

          Total funding:                         $920,000

      F.  Install hand railings onto Kaiser Stadium bleachers.

          Design:                                $150,000

          Construction:                          $800,000

          Total funding:                         $950,000

      G.  Modernize weightroom.

          Design:                                $250,000

          Construction:                          $1,000,000

          Equipment:                             $250,000

          Total funding:                         $1,500,000

      2.  Hahaione elementary school, Oahu

      A.  Design and construction for a covered play court.

          Design:                                $900,000

          Construction:                          $2,100,000

          Total funding:                         $3,000,000

      B.  Heat abatement and air-conditioning improvements for forty classrooms

          Design:                                $200,000

          Construction:                          $800,000

          Total funding:                         $1,000,000

      C.  Creation of an all weather fitness trail.

          Design:                                $500,000

          Construction:                          $1,500,000

          Total funding:                         $2,000,000

     SECTION 2.  The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2024-2025:

      1.  Maunalua Bay, Oahu

      A.  Construction of a loading dock on the Ewa side of the launch ramp to reduce congestion on the ramp.

          Planning and Permitting:               $400,000

          Construction:                          $4,400,000

          Total funding:                         $4,800,000

      B.  Improve sea wall to prevent further erosion damage on the Koko Head side.

          Planning and Permitting:               $400,000

          Construction:                          $3,400,000

          Total funding:                         $3,800,000

     SECTION 3.  In accordance with section 9 of article VII, of the Constitution of the State of Hawaii and sections 37-91 and 37-93, Hawaii Revised Statutes, the legislature has determined that the appropriations contained in this Act will cause the state general fund expenditure ceiling for fiscal year 2024-2025 to be exceeded by $        or      per cent.  The reasons for exceeding the general fund expenditure ceiling are that the appropriations made in this Act are necessary to serve the public interest and to meet the needs provided for by this Act.

SECTION 4.  The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the department of education for the purposes of this Act.

SECTION 5.  The sums appropriated for the respective capital projects set forth in section 2 shall be expended by the department of land and natural resources for the purposes of this Act.

     SECTION 6.  This Act shall take effect on July 1, 2024.

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; Eighteenth Representative District; Funds Exceeded

 

Description:

Appropriates funds for capital improvement projects for the benefit of the Eighteenth Representative District.  Appropriates funds exceeding the expenditure ceiling.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.